A recent post on LinkedIn suggested that contractors should use their “common sense” and just get on with it, rather than referring back to the structural engineer when something on site doesn’t match the drawings.

On the surface, it sounds practical. After all, contractors are on site every day, they know the building, and they understand how things fit together in reality. But there’s a problem with that line of thinking: common sense can’t calculate load paths.

The reality behind the drawings

As structural engineers, every design we produce is based on assumptions.

For example, when walls are removed, we may assume that an existing steel beam lies hidden behind plasterboard. We can’t always know what that beam was originally designed to carry, but we can calculate exactly what it needs to support going forward.

That’s why our drawings often include notes such as:
“This beam needs to be this size, or equivalent. Contractor to confirm.”

This instruction isn’t vague, it’s deliberate. It means that if the contractor uncovers something different from what we assumed, their next step is to come back to the designer.

Typical internal alterations

Why it matters

To the untrained eye, a beam of similar depth might look “close enough.” But here’s the danger: not all beams are created equal. A 152UC, a 152UB, and a 150-deep channel may look nearly identical, yet their performance can vary significantly.

One section may be prone to lateral torsional buckling, another might lack the stiffness required, and another could be more than adequate. The only way to know for sure is through design calculations. If a contractor relies on “common sense” to make that call, the risk is very real: overloading, hidden weaknesses, and ultimately, potential failure.

Clarity beats assumption

The Building Safety Act is unambiguous: the designer is responsible for the design. Contractors aren’t expected to carry that responsibility and shouldn’t have to.

The correct process is clear:

  1. Engineers make their assumptions explicit.
  2. Contractors confirm conditions on site.
  3. Any discrepancies are referred back to the structural engineer for reassessment.

This isn’t red tape. It’s safety. 

A beam isn’t safe simply because it “looks the right depth.”

Shape, section, restraint, and load conditions all play a role.


Contractors bring enormous value through their skill and experience on site. But they should never be left to make structural design decisions in isolation.

Common sense has its place, but when it comes to structural safety, clarity and collaboration will always beat assumption.

When thousands of UK buildings were found to contain a dangerous material, demolition was widely seen as the only answer, we believed there had to be a better solution.

This year, Michael Aubrey Structural Engineers was named Berkshire’s Construction & Engineering Company of the Year 2025 at the UK Business Awards for Berkshire and also received the Award of Excellence for Structural Engineering Services.

The recognition reflects not only our technical expertise but also our commitment to solving the UK’s toughest structural challenges in ways that protect people, places, and budgets.

One of the key reasons for our recognition is our Structural Detectiveâ„¢ methodology a proactive, approach to uncovering hidden structural issues before they become critical.

This means spotting:

  • Movement or subsidence
  • Historical alterations that weaken a structure
  • Environmental damage
  • Material degradation

By combining site investigation, diagnostics, and decades of engineering judgment, we give asset managers, developers, and public bodies the clarity they need to protect buildings and lives long before disaster strikes.

Award for RAAC Engineering John Staves


“We don’t just respond to failure we help clients understand the warning signs and avoid future risk,” says 

John Staves CEng FIStructE, Managing Director


The Problem That Needed a New Solution

Our approach to problem-solving was put to the test with Reinforced Autoclaved Aerated Concrete (RAAC) a material now known to pose serious safety risks in thousands of UK schools, hospitals, housing blocks, and public buildings.

While the usual fix has been demolition and costly rebuilds, we believed there had to be a better way.

RAAC Fix

John led the engineering design of the UK’s first in-situ structural repair solution for RAAC.

Instead of tearing down essential buildings, we engineered a solution to strengthen RAAC planks

This repair is:

  • Non-intrusive – no need to close or demolish the building
  • Cost-effective – saving millions in public money
  • Proven – independently verified, structurally certified, and already in use

As John explains:

“At a time when the UK is facing major infrastructure challenges, we’re proud to be delivering practical, innovative, and permanent solutions that protect both people and places.”

A Visit from Clive Jones MP

Our RAAC work has also caught the attention of local leaders.

clive jones MP

Image credit: Wokingham Today

Recently, we welcomed Clive Jones MP to our offices, where we shared our award-winning repair solution.

Clive was particularly interested in how our in-situ CFRP method avoids demolition, keeps essential buildings in use, and saves millions in public funds, all while ensuring safety.

He asked thoughtful questions about the technical process, the scale of the RAAC issue across the UK, and how innovation like this can support government priorities on infrastructure and sustainability.

John staves and Clive jones MP


We were encouraged by his offer to help raise awareness of our approach within government, showing that practical, cost-effective solutions to RAAC are not only possible but already here.



Why This Matters for the UK’s Built Environment

With over 30 years in the industry, we’ve learned three guiding principles:

  1. Preserve wherever possible
  2. Engineer with clarity
  3. Deliver with integrity

Whether it’s RAAC remediation, structural assessments, or advanced investigations, our approach is always about innovation without disruption.

As the UK’s infrastructure continues to age, we’re proving that engineering can be both technically brilliant and people-focused solving problems in ways that create safety, sustainability, and value for the long term.

About Michael Aubrey Structural Engineers
Founded over 30 years ago, Michael Aubrey Structural Engineers is a UK-based consultancy specialising in complex structural challenges. We work with commercial clients, developers, education trusts, public bodies, and asset managers across the UK, delivering solutions with integrity, clarity, and innovation.

Need structural advice? Call us on 0118 962 9666


If you’ve ever been told, “We don’t do temporary works,” by a structural engineer, you’re not alone.

It’s one of the most common pain points for contractors and developers.

You’re trying to get a steel frame propped, a basement dug safely, or a wall retained mid-demolition and suddenly the structural engineer steps back.

So, why do most structural engineers avoid designing temporary works? And how can you manage that risk without delaying your programme?

Let’s break it down.

1. Temporary Works Are a Specialist Discipline

While permanent works are designed for long-term use under predictable loads, temporary works are often riskier, more variable, and require a different skill set:

  • Changing load paths
  • Construction sequencing
  • Unknown site conditions
  • Short-term safety-critical elements

Most consulting engineers are trained and insured for permanent structure design, not the temporary measures needed during construction. That’s why they won’t take it on: it’s outside their remit and professional indemnity cover.

2. They’re Not Covered by PI Insurance

Designing temporary works comes with higher risk. Props collapsing, excavations failing, or inadequate sequencing can result in injury, delay, or collapse. The more complex the greater the requirements for contractor competence.

Unless a compnay has experience in temporary works design,  it’s not worth the risk, which is why many structural engineers draw a clear line.  But realistically they know more about the loadpaths, permanent and temporary, so should be well placed to manage the temporary situation.  Taking this knowledge into the construction phase is invaluable.

temporary works

3.  They Can’t Guarantee Construction Methodology

Temporary works often depend on how something is built, not just what is built.

For example:

  • Will the builder support the wall before or after cutting the opening?
  • Are props installed on solid ground or backfilled subsoil?
  • Is access possible to erect the system safely?

Most consulting engineers aren’t on site and aren’t supervising construction, so they can’t verify these critical assumptions and therefore won’t take responsibility. 

But construction is collaborative. 

Engaging the permanent works designer in the build phase not only meets Building Safety Act requirements, but could improve knowledge transfer from design to construction phases.  What can’t easily be conveyed on drawings of a permanent solution is ‘why’.

4.  We Work Collaboratively to Keep the Structure Safe

While we may not design temporary works directly, we play a vital role in keeping the structure safe during construction.

As structural engineers, we understand the existing structure intimately. That puts us in the best position to advise the contractor on:

  • Where loads are being transferred during partial demolition
  • What needs supporting and when
  • How to phase permanent works to maintain structural integrity

We work collaboratively with contractors and temporary works designers, ensuring that the permanent and temporary designs are coordinated and that site safety isn’t compromised.

structural engineer temporary works

5.  Temporary Works Are Best Led by the Contractor’s Team

This is why temporary works design is usually the contractor’s responsibility. Under CDM Regulations, the contractor must ensure works are carried out safely and that includes temporary conditions.

Specialist temporary works engineers, often engaged by the contractor, understand build sequencing, shoring systems, and installation constraints. They design for real-world conditions.

6.  How to Manage This on Your Project

  • Flag it early: If your project needs propping, façade retention, needling, or basement excavation, raise it before site start.
  • Appoint a specialist: Ideally the structural engineer on the project who has relevant experience and insurance.
  • Work as a team: Encourage collaboration between the contractor and structural engineer.
  • Don’t delay: Waiting until the structure is half-demolished before asking for temporary works design is a recipe for delay (or worse).

In Summary

Most structural engineers aren’t being awkward when they say “We don’t design temporary works.” They’re being responsible.

It’s a specialist discipline with high risk, unique methods, and specific legal duties.

But that doesn’t mean we disappear, far from it.

We work closely with contractors to help identify risks, suggest safe sequencing, and keep the structure stable while the permanent alterations are being made.

Got a complex scheme or unsure how to plan the temporary staging?

Talk to us early, we’re here to help the structure stand up from start to finish. Call us 0118 962 9666